Customs and tax exemption for the assets of a licensed project

Service providerBasrah Investment Commission – Technical Section / Exemptions Division
DurationApproximately (49–56) working days, depending on the sectoral authorities' readiness to respond
FeesService fee: (1,000,000) one million Iraqi dinars
CategoryInformation service

Procedure description

A procedure setting out the steps and requirements for a licensed project to obtain customs and tax exemption for the materials, equipment, and machinery required for its establishment, in addition to tax exemption on the project's profits. Exemption applications are reviewed by the Technical Section / Exemptions Division, and exemption letters are issued addressed to the competent financial and customs authorities.

Target audience: Owners of licensed investment projects

Conditions and eligibility

  • The project must hold a valid investment license

  • The materials must be necessary for establishing or operating the licensed project

  • The assets must be brought into Iraq within (3) years

Required Documents

  • An official letter from the company requesting customs and tax exemption

  • A copy of the investment license (in the case of an expansion, accompanied by the administrative expansion order)

  • A written undertaking from the authorized manager not to use the materials outside the scope of the project, and to notify the Commission upon their arrival at the project site

  • A letter of authorization to deal with the General Customs Authority and complete the import procedures

  • A list of the materials to be exempted (name, details, quantity in figures and words, HS code, port of entry) in four copies and in both Arabic and English

  • Engineering drawings showing the locations and areas of the materials, equipment, and machinery to be exempted

  • An approved calculation method for the requested quantities, issued by an accredited consultancy office

  • Where generators or electrical transformers are requested: the load calculation method and the electrical drawing, and a letter of approval from the Ministry of Electricity

  • A letter certifying the actual need for the materials, and a letter certifying the project's completion percentage from an accredited consultancy office

Processing steps

1

Submitting the application

Receiving the application from the company's authorized representative and referring it to the Technical Section and then to the Exemptions Division.

Administrative and Financial Department1 working day
2

Reviewing the application

A committee of (3) staff (technical and legal) reviews the application and prepares a memorandum of any incomplete requirements.

Exemptions DivisionAbout 3 working days
3

Corresponding with the sectoral authorities

Corresponding with the relevant ministries (Industry, Electricity, Oil, Health, Interior / Civil Defense, security agencies) according to the type of materials.

Office of the Commission President
4

Receiving the responses

Receiving and recording the sectoral authorities' replies.

Administrative and Financial Department10 – 15 working days
5

Issuing the exemption letter

Issuing the customs and tax exemption letter addressed to (Customs, Taxes, the Ministry of Finance, the security agencies, the Border Ports Authority, and the investor).

Exemptions Division
6

Electronic and paper dispatch

Sending the letter through the electronic customs-exemption system and in hard copy.

Technical Section / Exemptions Division

Legal basis

Frequently Asked Questions

May the service fee be paid in cash?
The service fee is paid to the Commission, and the payment method is determined in accordance with its instructions in force.
How is the exemption letter sent to Customs?
It is sent through the electronic customs-exemption system and in hard copy to the authorities it is addressed to.
How long is the exemption letter valid?
From one to three years from the date of issue, depending on the case.
The service fees and periods are based on what is published in the National Investment Commission's services on the Ur platform, and are subject to update in accordance with the Basrah Investment Commission's instructions in force.

Working Hours: During official working hours (Sunday – Thursday)

Need help with this procedure?

Contact the One-Stop Shop Department at the Basrah Investment Commission to ask a question or start your transaction.